Xiong'an Citizen Service Center — Steel Member Fabrication Case
Public Infrastructure Projects
workshop 40

Xiong'an Citizen Service Center — Steel Member Fabrication Case zy-tit-icon

Project Overview

Project Name: Xiong'an Citizen Service Center — Steel Member Fabrication Case

Location: Xiongan District, Beijing City

Project Type: Large-scale Civic Event Cultural Center

Project Area: 99,600 square meters

Planned land area:24.24 hectares

Commencement and completion dates:2017年12月-2018年4月

Total investment: one hundred million

Send Inquiry

Project Scale

Programme is the other variable. Start in December 2017, finish in April 2018: five months, which works out at close to 20,000 m² a month. No fabrication shop waits for the complete drawing set at that pace.

Our role was the supporting one. The Tianjin plant of China Construction Steel Structure (North Region) placed part of the member fabrication with us; we have worked as their strategic partner for years. A fabrication subcontract inside a main contractor's system is judged on responsiveness rather than on any single process. Can the shop set up the same day the drawing lands? Can it re-cut the night a revision arrives? Is there spare capacity when the plant's own machines are full?

Project Area 99,600m²
Planned land area 24.24 hectares

The Citizen Service Center opened in June 2018 and carries public services, the planning exhibition, temporary offices and an ecological park — the first piece of Xiong'an's functional programme to be delivered. Total floor area is 99,600 m² on a 242,400 m² site.

Put 99,600 m² on 242,400 m² of land and the plot ratio lands at 0.41. That number tells you what the building is: not a single tower but a campus, several low-rise buildings set apart with planting and pedestrian routes between them 〔building count and storeys to be confirmed〕. For a steel supplier that means the difficulty is not tonnage. It is variety — many sections, small batches, released building by building.

Scope of Fabrication

Our package ran from cutting to numbered delivery: cutting, fit-up, welding, straightening, shot blasting to Sa 2.5, coating, marking, packing and dispatch. Site erection and grouting were outside our scope:

workshop 36
Main structure
steel structure building (116)
Secondary framing and bracing
workshop 35
Floor system
steel structure building (167)
Auxiliary industrial buildings
workshop 42
Large-span roof systems
01

Five months, with drawings chasing the site

Projects at this speed run design, detailing and construction in parallel, and fabrication sits at the front of that chain — a drawing a day late pushes everything behind it. We moved detailing support into the shop: a fabrication issue first, plain sections and connection plates stocked ahead, and production cut into building-by-building batches so the first building erected was the first one made. Nobody waited for the full set.

02

On a national key project, quality lands on the welders and the paperwork.

The specification was strict, so the company pulled its core crew onto the job and put the production director personally in charge of quality. Three controls did the work. First-off inspection — no batch released until the first piece passed. Certified welders only, with every weld traceable through member number, welder ID and shift. Dimensional deviation held in jigs, not corrected afterwards with heat.

03

Members are lifted as they arrive, so there is no window for rework

Site space was squeezed to the limit and components went from trailer to crane. A damaged coating means touching up inside the erection cycle. We used soft slings and timber packing between layers, turned member marks outward, and braced long pieces against transport distortion.

04

Tight Construction Schedule

The project had strict delivery deadlines to support factory commissioning plans, requiring efficient production coordination and installation management.

Project Advantages

01.

Fast Construction Speed

Capacity is elastic. The point of a strategic partnership shows up on peak days: when the plant's own lines are full, we absorb the overflow and the delivery date does not move.

02.

High Load Capacity

The documentation closes. What leaves the shop is not a dispatch note but a pack — mill certificates, re-test reports, NDT records, coating thickness logs and a member schedule — so site inspection and the final handover file both reconcile.

03.

Flexible Expansion Capability

The quality system already existed. We hold ISO 9001, EN 1090 and CE, run 30,000 tons a year, and fabricate to the inspection habits of export work, which means a domestic key project does not need a parallel procedure bolted on.

Project Results

Fabrication was completed to the project's milestones in April 2018 and met the member acceptance standard. The Citizen Service Center opened in June 2018, with public services, the planning exhibition, temporary offices and the ecological park all in use.

workshop 44

Why Choose Our Steel Structure Solutions

A strategic partner, not a spot supplier. Long-term partner of China Construction Steel Structure's Tianjin plant, 30,000 tons a year, with capacity left when peak batches land.
Export standards on a domestic key project. ISO 9001, EN 1090 and CE all running, with inspection records kept the way export work demands.
Paperwork travels with the steel. Mill certificates, re-test reports, NDT records, coating logs and member schedules in one pack, ready for site inspection.
Detailing that does not wait for drawings. Shop-based support, fabrication issue the same day a drawing lands, common sections and plates stocked ahead.
Production cut to erection sequence. The building going up first is the building made first, no waiting on the complete set.
Coating done in-house. A new coating and secondary-steel shop added in 2025 keeps blasting through to topcoat on one line, nothing outsourced.

This project continues to serve as a strong example of our ability to support world-class manufacturing infrastructure with reliable steel structure solutions.