Xiqing District Commercial City, Tianjin
Commercial Projects
workshop 32

Xiqing District Commercial City, Tianjin zy-tit-icon

Project Overview

Project Name: Xiqing District Commercial City, Tianjin

Location: No. 6, Jinjing Road, Xiyongmen Street, Xiqing District, Tianjin

Project Type: Large-scale contiguous commercial clusters

Project Area: 210,000 m² (Phase I Plant Area)

Total Site Area: 8000m²

Completion Year: 2020

Project Status: Successfully Delivered

Send Inquiry

Project Scale

The project is located in Xiqing District, Tianjin, with a gross floor area of 8,000 m² and a steel frame as the primary structural system. We mobilised on site in March 2020 and handed over in June, holding net construction time to roughly 120 days. Xiqing sits in the manufacturing belt on Tianjin's western side, surrounded by equipment makers, automotive parts suppliers and warehousing operators. The owner's brief came down to two points: equipment loads would not be evenly distributed once production lines were installed, so floors and column grids had to carry retrofit allowance; and the production start date was already fixed, which ruled out any sequential approach where civil works finished before steel erection began.

Total Development Area 8000 m²
Phase I Construction Area 210,000 m²

The building was designed as a single-storey industrial workshop with a small annex. The column grid followed the process equipment layout, and main frame spans and bay spacing were back-calculated from the equipment lifting aisles and crane runway positions — cheaper now than reworking a column that lands in the wrong place later.

Scope of Structural Work

Our scope ran from component fabrication through envelope closure. Civil foundations were excluded, though we coordinated on anchor bolt embedment:

workshop33
Main structure
workshop 34
Secondary framing and bracing
workshop 35
Foundation interface
workshop31
Coating and fire protection
Steel structure workshop10
Auxiliary industrial buildings
Steel structure workshop14
Large-span roof systems
01

A March start put us straight into the cold window.

Tianjin warms up during the day in March, but nights still sit near 0 °C, and neither the anti-corrosion topcoat nor the fire protection coating cures reliably in that range. The answer was to move as much wet work into the shop as possible: shot blasting, primer and topcoat all completed in the factory, with only touch-up on transport and lifting damage left for site. Fire protection that genuinely had to be applied on site was scheduled into the warmer daylight hours, built up in thin passes with thickness controlled and intervals respected — slower per coat, but no rework.

02

With 120 days on the clock, civil works and steel erection had to run in parallel

Components were dispatched from the factory in batches while foundations were still being poured. Site erection followed the sequence main frames, then secondary framing, then envelope, with roof closure pulled forward as a whole so that the roof was sealed before the June rains set in — insulation that takes on water has to be stripped and replaced.

03

At 8,000 m², the sheer number of column bases made embedment tolerance the real risk.

Once an anchor bolt group drifts beyond allowable deviation, the only options on erection day are drilling out or re-plating on site, and both cost schedule and structural margin. We fixed each bolt group with purpose-made steel templates and re-surveyed centrelines and levels group by group before pouring, with someone tracking the pour to catch any movement from vibration.

04

Tight Construction Schedule

The project had strict delivery deadlines to support factory commissioning plans, requiring efficient production coordination and installation management.

Project Advantages

01.

Fast Construction Speed

Factory prefabrication and numbered dispatch, with bolted connections doing most of the work on site, kept wet trades and field welding to a low level. That is the precondition for a 120-day programme, and it also meant the site did not come to a standstill every time the weather turned.

02.

High Load Capacity

The coating system was built up in one continuous operation in the shop, which is far more controllable than spraying on site. Steel structures rarely fail because of the steel itself; they fail where the coating is breached and corrosion starts. Shop-applied coating plus proper transport protection removes a good part of that hidden cost.

03.

Flexible Expansion Capability

Bracing was configured for two-way load transfer, with column bracing and roof horizontal bracing forming a complete lateral system. That shows up later, when an owner adds an overhead crane or mounts new equipment on the roof: the structure still has margin, and nothing has to be torn down and rebuilt..

04.

Long-Term Durability

High-quality materials and advanced fabrication standards ensured long-term operational stability.

Project Results

The workshop was completed and handed over on schedule in June 2020, with 8,000 m² of gross floor area. Main structure erection and envelope closure were both finished ahead of the peak rainy period, leaving the owner time to bring equipment in.

steel structure building (56)

Why Choose Our Steel Structure Solutions

Large industrial project experience
Automotive manufacturing facility expertise
Precision steel fabrication capability
Strict quality management system
Fast project delivery performance
Proven experience with international brand projects

This project continues to serve as a strong example of our ability to support world-class manufacturing infrastructure with reliable steel structure solutions.